Traffic & Parking

  • Parking at the Park Drive & Clarke Street Playground remains unavailable due to fencing of the skatepark staging area.

  • Worthen Road parking in front of the construction site remains reduced; spaces have been removed.

  • New this week: Utility work begins on Park Drive. Expect lane restrictions, alternating one-way traffic under police detail, and additional parking restrictions along the active work zone.

Noise

  • Trucks will continue coming to and from the site.

  • New this week: Park Drive utility work will generate saw-cutting, excavation, and compaction noise during permitted work hours.

Bus & Pedestrian

  • The sidewalk along Worthen Road will have temporary interruptions above the site fence.

  • New this week: Temporary sidewalk closures and pedestrian detours on Park Drive at the trench location. Flaggers will direct pedestrians around the work zone.

Schedule Changes

  • No changes to the project schedule this week.

Utilities & Services

  • Utility work begins on Park Drive the week of August 10. Any planned service interruption to abutting properties will be noticed in advance.

---

Next
Next

Construction Begins July 6 — What to Expect