  • Steel H-pile installation began the week of October 26 and continues through the winter. Pile driving is the loudest activity on the project to date.

  • Full perimeter site fencing inside the wetland buffer zones is going up now. A final DEP site walk was completed Thursday, October 29.

  • Clarke Street water main work ongoing through November. Pedestrian access along Clarke Street remains open until the work is complete.

 

Traffic & Parking

  • Parking at the Park Drive & Clarke Street Playground remains unavailable while the skatepark staging area is fenced. The replacement parking lot is expected to be complete in December.

  • Worthen Road parking in front of the construction site remains reduced; spaces have been removed.

  • Clarke Street remains periodically closed to through traffic at the active work zone until the water main work is complete.

  • Truck traffic increases site-wide in November.

 

Noise

  • Trucks will continue coming to and from the site throughout the month.

  • Steel H-pile installation began the week of October 26 and continues into the winter. Pile driving produces repetitive impact noise and is limited to permitted work hours.

  • Full site preparation begins in November, expect increased construction activity.

  • All work remains within permitted work hours.

 

Bus & Pedestrian

  • The sidewalk along Worthen Road will have temporary interruptions alongside the site fence.

  • Pedestrian access along Clarke Street remains open until the water main work is complete. Temporary walkways and marked detours route pedestrians around the work zone.

  • Temporary walkways around the skatepark staging area remain in place until the staging fence comes down.

  • With the full perimeter fence going up inside the buffer zones, the site perimeter is expanding and walking routes across the site area are permanently closed.

 

Schedule Changes

  • The Conservation Commission / DEP review is in its final step, with a final DEP site walk completed on Thursday, October 29 giving full go-ahead. Full site fencing and erosion controls inside the buffer zones are proceeding.

 

Utilities & Services

  • Clarke Street water main installation is finishing up. Any additional planned service interruption to abutting properties will be noticed in advance.

 